Post by LCACAT on Mar 10, 2020 8:59:32 GMT -5
Any word on when the siding will be removed from the RAC? I thought it was to be done by now.
|
|
|
Post by bigcatfan on Mar 10, 2020 9:17:18 GMT -5
Work has begun removing the glass on the east side of the building. That's a tough job in that we can't get more than a day or two break from the rain, so they are already way behind schedule.
|
|
Deleted
Deleted Member
Posts: 0
|
Post by Deleted on Mar 10, 2020 9:43:22 GMT -5
I check usually some days after class, the glass has been removed and They’ve started putting up metal strips for the wood paneling
|
|
|
Post by LCACAT on Mar 10, 2020 10:37:55 GMT -5
Thanks
|
|
|
Post by bigcatfan on May 7, 2020 8:02:28 GMT -5
Ramsey facade work is progressing. Also, baseball lot now closed and demolition work has begun to make way for the new parking deck.
|
|
|
Post by CharlotteCat on May 7, 2020 8:06:40 GMT -5
Ramsey facade work is progressing. Also, baseball lot now closed and demolition work has begun to make way for the new parking deck. Can anyone take a pic of the work being done on Ramsey? How is the new entrance sign coming along? a pic of that would be nice too.
|
|
|
Post by scottbeach on May 7, 2020 9:11:31 GMT -5
Work has begun removing the glass on the east side of the building. That's a tough job in that we can't get more than a day or two break from the rain, so they are already way behind schedule.
No different than when they originally built the place.
|
|
|
Post by catdaddy85 on May 7, 2020 20:31:17 GMT -5
Sign work very slow it seems. Was working on the right when we went by the other day. No lettering was up yet.
Nothing was going on at the baseball field that I saw.
|
|
|
Post by realoldcatamount on May 8, 2020 18:26:02 GMT -5
The east side of the building is basically finished. Top two-thirds is gray and bottom third is red (brick color). Why not purple instead of brick red? The parking deck work is underway on the baseball field parking lot. Area is completed fenced with construction trailers and heavy equipment on site. A couple big holes have been dug. Might be the last time we'll be able to see the baseball field from Forest Hill Road and the Ramsey Center. Workers are back at the Apodoca Building (STEM) after almost two weeks of closure for sanitizing following positive tests for COVID-19 from several construction workers. Life is Cullowhee is really strange nowadays and will not likely be the same for a long time (months? years?).
|
|
|
Post by The Cats on Jun 10, 2020 13:04:36 GMT -5
|
|